A E Yates Ltd. are currently completing Phase 1 of Harworth Group plc‘s new development which will include “up to 1.1 million sq ft of logistics and manufacturing space at its site in Wingates, Bolton, with the potential to create up to 1,500 new jobs.”
At present we are continuing with the Road Box Construction and soil improvement layers which are due to be complete next week.
We are also progressing the Temporary drainage and associated works which are due to also be finalised next week.
The rising main installation up the Current A6 has also started and progressing well, this is currently on or Infront of programme.
Open Reach lowering works and some of the Swapping out of poles on the ATS were completed prior to the shutdown, the remainder of the swapping out of poles are due to commence and be finalised in the coming weeks.
Further works such as install of the permanent drainage and installation of ducting and kerbs will follow on shortly.